The project consists of two stages :
Evaluation of existing Amiriya Pharmaceutical Plant utilizing testing equipment to measure different spaces flow rates and pressure relations, equipment performance. A report was prepared highlighting deficiencies observed for the different classes.
A layout with an area of 120,000 m² which consists of 14 buildings related to plants and warehouses. The following are the areas of the main buildings:
Block A: 17,000 m² , Block B: 19,000 m² , Block C: 7,611 m² Block D: 1,450 m² , Block F: 2,200 m²
Heating, ventilation and air conditioning design of warehouse, production building of total area about 70,000m². The total tonnage is 3700 TR. The production building is classified under pharmaceutical industries where special care is required for indoor conditions control in addition to airborne particulate control.
MEP WORKS (Design) cold water systems Moles storage tanks C.W piping and pumps fermentation tanks e.w piping & Pumps.
The factory is about 4500sq.m (plot area)and specialized for animal feed and veterinary vaccines this factory includes the following buildings:-
– Warehouses (finished and semi finished products.
– Office Building (Basement, Ground & 4 typical floors.
– Production area
Air Conditioning And Ventilation Design Of Refrigeration Production Building And Carpentry Production Building In Bahget Factory Complex In 6 Of October Industrial Zone.
Air Conditioning And Ventilation Design Of Zamil Factory For Steel Production.