2*60000TR DCP with a chilled water network to serve the new administrative capital.
The project is the installation of the first plant and the entire network.
The plant is utilizing water cooled centrifugal chillers and Gas fire, absorption chillers.
A 15000TR (3 Tanks) chilled storage tanks are used. The network is 57 km reinsulated buried pipes with values for each plot and buried
value chambers on the main distribution.
(DCP + CHW\N) Design, Tender, construction supervision