JABAL OMAR DCP

  • Client: Saudi Tabreed
  • Location: KSA - Mecca
  • Chiller Type Capacity : 55,000 TR
  • Pumping Concept: Variable Primary
  • Make up water: Treated Sewage Effluent
  • Construction Cost: 450 Million SAR
  • Start Date: 2011
  • Status: Completed

JABAL OMAR DCP

The project consists of a DCP providing 55,000 Refrigeration Tonnage chilled water supply to surrounding buildings in Jabal Omar Development.
The cooling plant employs water- cooled electric driven centrifugal chillers and Variable primary flow pumping scheme located in the Basement levels of a Hotel Tower, distribution of chilled water to various buildings via a network of piping system that runs either underground or within a tunnel.

Scope of Work:

Prepare EPC contract & Design Review.